Land use: Earthworks associated with the remediation of potential contaminated land across the “Stage 1” area of the…
Earthworks associated with the remediation of potential contaminated land across the “Stage 1” area of the proposed redevelopment of Pakuranga Plaza. Note application has been made ahead of the full Plaza “Stage 1” development application, due to a detailed site investigation DSI unable to be undertaken and prepared to assess the full extent of potential contamination beneath the existing buildings and structures. **All Costs and documents can be found under DIS60412790**
Land use · Auckland · lodged 13 Apr 2023
- Council
- Auckland
- Consent number
- LUC60417510
- Kind
- Land use consent
- Subtype
- Earthworks Non-Residential
- Application
- New consent (s88)
- Activity status
- Discretionary
- Lodged
- 13 Apr 2023
- Decided
- 13 Feb 2024
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 53
- Council charges
- $4,336
- Legal description
- LOT 2 DP 158869; LOT 1 DP 53433; LOT 1 DP 65748; PT LOT 5 DP 55286; LOT 1 DP 93910; LOT 2 DP 93910; SEC 24 BLK II OTAHUHU SD; PT LOT 10 DP 55286; LOT 2 DP 65748; LOT 1 DP 158869
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
On 2 properties, matched by the legal description the council gave.
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |