Land use: large-scale earthworks including a new retaining wall, and earthworks within 1.5m of underground stormwater…
large-scale earthworks including a new retaining wall, and earthworks within 1.5m of underground stormwater and foul sewer pipes
Land use · Dunedin City · lodged 22 Dec 2022
- Council
- Dunedin City
- Consent number
- LUC-2022-553
- Kind
- Land use consent
- Subtype
- Boundary
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 22 Dec 2022
- Decided
- 8 Feb 2023
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 20
- National environmental standard
- NES Assessing and Management Contaminants in Soil to Protect Human Health
- Council charges
- $1,042
- Legal description
- LOT 1 DP 517597
How it went
- Application lodged
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Dunedin City's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 3 | 8 | 0 | — | 0 |
| 2023/24 | 1 | 3 | 0 | 0 | 0 |
| 2022/23 | 0 | 2 | 0 | 0 | 0 |
| 2021/22 | 2 | 1 | 0 | 0 | 0 |
| 2020/21 | 5 | 1 | 0 | 0 | 0 |