Granted

Land use: Remedial works following Environment Court Decision ( 2017) NZEnv C18.-Enforcement Order [2017] NZEnvC 18…

Remedial works following Environment Court Decision ( 2017) NZEnv C18.-Enforcement Order [2017] NZEnvC 18 requires remediation involving the removal and lawful disposal of surface fill (containing asbestos); the removal and lawful disposal of the intermediate soil and base layers of vegetation and refuse; and reforming the site to a safe profile.

Land use · Auckland · lodged 31 Aug 2017

Council
Auckland
Consent number
LUC60307014
Kind
Land use consent
Subtype
Vegetation Removal
Application
New consent (s88)
Activity status
Discretionary
Lodged
31 Aug 2017
Decided
17 Nov 2017
Notification
Not notified
Hearing
No
Decided by
Independent commissioner(s)
Appealed to the Environment Court
No
Working days to decide
55 (over the statutory limit)
Council charges
$7,532
Legal description
Lot 1 DP 417809

How it went

  1. Application lodged
  2. Granted by independent commissioner(s)

Properties

On 1 property, matched by the legal description the council gave.

Auckland's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/255,2183,727—3427
2023/241,0062,94223942
2022/239392,72621222
2021/223,2112,43542117
2020/211,3263,9624832