Land use: To construct and maintain two geotechnical bores (BQ32/0865 and BQ32/0866) to support pump testing and…
To construct and maintain two geotechnical bores (BQ32/0865 and BQ32/0866) to support pump testing and monitoring and to undertake a reinjection test (discharge of water to groundwater) to inform the feasibility of a Ground Sourced Heat Pump for Naenae Pool and Fitness Centre.
Land use · Greater Wellington Regional · lodged 3 Jun 2022
- Council
- Greater Wellington Regional
- Consent number
- 38366*
- Kind
- Land use consent
- Subtype
- LUC - BORES
- Application
- New consent (s88)
- Activity status
- Controlled
- Lodged
- 3 Jun 2022
- Decided
- 5 Aug 2022
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 14
- Council charges
- $2,526
- Legal description
- Lot 2 DP 17448
How it went
- Application lodged
- Council told the applicant there are affected neighbours
- Council asked for more information (s92)
- Applicant provided the information
- Applicant answered: neighbours’ approvals, or notify them
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Processed with
- 38461* — Discharge permit, granted
Greater Wellington Regional's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 68 | 39 | 0 | 0 | 6 |
| 2023/24 | 188 | 25 | 0 | 0 | 6 |
| 2022/23 | 80 | 36 | 2 | 0 | 6 |
| 2021/22 | 35 | 40 | 1 | — | 74 |
| 2020/21 | 92 | 26 | 1 | 98 | 39 |