Land use: Establishment of a telecommunications facility.
Land use · Hutt City · lodged 23 Apr 2025
- Council
- Hutt City
- Consent number
- RM250069
- Kind
- Land use consent
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 23 Apr 2025
- Decided
- 27 May 2025
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 20
- National environmental standard
- NES Telecommunications Facilities
- Council charges
- $4,995
- Legal description
- LOT 14 DP 15878
How it went
- Application lodged
- Suspended until charges were paid
- Resumed after charges were paid
- Processing paused at the applicant’s request (s91A)
- Processing resumed
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Hutt City's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 59 | 9 | 0 | 0 | 0 |
| 2023/24 | 51 | 7 | 0 | 0 | 0 |
| 2022/23 | 57 | 5 | 0 | 1 | — |
| 2021/22 | 46 | 3 | 0 | 1 | — |
| 2020/21 | 43 | 16 | 0 | 0 | 0 |