Granted

Discharge permit: To discharge human wastewater up to a maximum of 22,300 litres per day from the Pelorus campground,…

To discharge human wastewater up to a maximum of 22,300 litres per day from the Pelorus campground, motorhome, public toilets and cafe facilities to land on Section 3 SO 427361 and Section 64 Block VIII Heringa SD.

Discharge permit · Marlborough District · lodged 11 Jun 2024

Council
Marlborough District
Consent number
240563.01
Kind
Discharge permit
Subtype
DTL
Application
New consent (s88)
Activity status
Discretionary
Lodged
11 Jun 2024
Decided
12 Nov 2024
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
15
Council charges
$6,736
Legal description
Easting: 1647764, Northing: 5428214

How it went

  1. Application lodged
  2. Suspended until charges were paid
  3. Resumed after charges were paid
  4. Council asked for more information (s92)
  5. Applicant provided the information
  6. Council commissioned an expert report (s92(2))
  7. Commissioned report received
  8. Granted

Properties

On 5 properties, matched by the legal description the council gave.

Marlborough District's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/254129000
2023/244540000
2022/2354280011
2021/223314010
2020/214528011