Land use: Consent is sought to construct a principal dwelling; infringing height in relation boundary and height, and a…
Consent is sought to construct a principal dwelling; infringing height in relation boundary and height, and a minor dwelling; infringing height in relation to boundary, with associated earthworks and retaining structures exceeding 1.5m height within the 1.0m side yard setback.
Land use · Auckland · lodged 20 Sep 2017
- Council
- Auckland
- Consent number
- LUC60308066
- Kind
- Land use consent
- Subtype
- Earthworks Residential
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 20 Sep 2017
- Decided
- 9 Feb 2018
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 17
- Council charges
- $3,606
- Legal description
- Lot 2 DP 479120
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |