Coastal permit: Consent to undertake dredging of 10,770m3 to gain all tide boat ramp access, and maintenance dredging…
Consent to undertake dredging of 10,770m3 to gain all tide boat ramp access, and maintenance dredging of 850m3 every five years for a 35-year term. To generate underwater noise from impact/vibratory piling to place navigational markers
Coastal permit · Auckland · lodged 9 Jun 2020
- Council
- Auckland
- Consent number
- CST60358415
- Kind
- Coastal permit
- Subtype
- Dredging
- Application
- New consent (s88)
- Activity status
- Discretionary
- Lodged
- 9 Jun 2020
- Decided
- 17 Nov 2020
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 98 (over the statutory limit)
- Council charges
- $23,772
- Legal description
- LOT 7 DP 513013, LOT 24 DP 513013, 1/4 SH LOT 20 DP 513013
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
On 4 properties, matched by the legal description the council gave.
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |