Land use: **BUNDLED** TO CONSTRUCT A NEW WASTEWATER PIPE BRIDGE AND ASSOCIATED WORKS TO REPLACE THE EXISTING PIPE…
**BUNDLED** TO CONSTRUCT A NEW WASTEWATER PIPE BRIDGE AND ASSOCIATED WORKS TO REPLACE THE EXISTING PIPE BRIDGE IN THE SAME LOCATION
Land use · Gisborne District · lodged 1 Mar 2021
- Council
- Gisborne District
- Consent number
- LR-2021-110244-00
- Kind
- Land use consent
- Subtype
- Use of bed of lake or river - structure, disturb bed, introduce plants or plant, deposit, reclaim, habitats of plants, habitats of animals, other - please specify
- Application
- New consent (s88)
- Activity status
- Discretionary
- Lodged
- 1 Mar 2021
- Decided
- 1 Apr 2021
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 22 (over the statutory limit)
- Council charges
- $0
- Legal description
- LOT 20 DP 4308 LOT 7 DP 4308
How it went
- Application lodged
- Granted
Properties
Not matched to a property.
Gisborne District's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 134 | 72 | 5 | 1 | 0 |
| 2023/24 | 88 | 57 | 0 | 1 | 3 |
| 2022/23 | 7 | 60 | 0 | 3 | 1 |
| 2021/22 | 81 | 38 | 0 | 3 | 1 |
| 2020/21 | 37 | 33 | — | 5 | 5 |