Subdivision: Resource consent is required under the Auckland Unitary Plan (AUP) for the construction of six dwellings…
Resource consent is required under the Auckland Unitary Plan (AUP) for the construction of six dwellings that utilise the AHiRTB sta ndard and do not comply with yard, HIRTB and earthworks standards, and for fee simple subdivision. Overall, land use consent and sub division consent are both required as a restricted discretionary activity.
Subdivision · Auckland · lodged 19 Aug 2021
- Council
- Auckland
- Consent number
- SUB60384515
- Kind
- Subdivision consent
- Subtype
- Freehold
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 19 Aug 2021
- Decided
- 11 Apr 2022
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 53
- Council charges
- $5,696
- Legal description
- Lot 41 DP 45393
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Processed with
- LUC60384516 — Land use, granted
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |