Granted

Land use: To undertake earthwork activities associated with the construction of stormwater infrastructure as well as…

To undertake earthwork activities associated with the construction of stormwater infrastructure as well as the diversion and discharge stormwater associated with the operation of the stormwater infrastructure

Land use · Waikato Regional · lodged 4 Dec 2020

Council
Waikato Regional
Consent number
AUTH142634.01.01
Kind
Land use consent
Subtype
Land - disturbance
Application
New consent (s88)
Activity status
Discretionary
Lodged
4 Dec 2020
Decided
10 Feb 2021
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
20
Council charges
$3,073
Legal description
1795539,5816816

How it went

  1. Application lodged
  2. Granted

Properties

Not matched to a property.

Processed with

Waikato Regional's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/252911033—46
2023/24521161——
2022/23154——418
2021/22159—2921
2020/2118611814038