Granted

Land use: Consent is required in terms of the section 127 of the Resource Management Act 1991 for a discretionary…

Consent is required in terms of the section 127 of the Resource Management Act 1991 for a discretionary activity to change condition (1). Change the approved joinery from timber to powder coated aluminum joinery with timber with timber surrounds as detailed on the application plans and Change the approved roofing material change from concrete tiles to metal pan profile roofing.

Land use · Auckland · lodged 1 Feb 2023

Council
Auckland
Consent number
LUC60397192-A
Kind
Land use consent
Subtype
Demolition
Application
Change of conditions (s127)
Activity status
Discretionary
Lodged
1 Feb 2023
Decided
13 Mar 2023
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
27
Council charges
$4,941
Legal description
Pt Lot 1 DP 34427

How it went

  1. Application lodged — Change of conditions (s127)
  2. Granted — Change of conditions (s127)

Properties

On 2 properties, matched by the legal description the council gave.

Auckland's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/255,2183,727—3427
2023/241,0062,94223942
2022/239392,72621222
2021/223,2112,43542117
2020/211,3263,9624832