Granted

Land use: To undertake disturbance to the bed of a tributary of Porirua Stream during the placement of a rock rip-rap…

To undertake disturbance to the bed of a tributary of Porirua Stream during the placement of a rock rip-rap structure, including any associated discharge and temporary diversion of the stream, to repair a scoured/eroded area in the stream bed and banks, downstream of an existing culvert''s outlet.

Land use · Greater Wellington Regional · lodged 7 Nov 2016

Council
Greater Wellington Regional
Consent number
WGN170103-[34381*]
Kind
Land use consent
Subtype
LUC - STREAMWORK
Application
New consent (s88)
Activity status
Discretionary
Lodged
7 Nov 2016
Decided
3 Feb 2017
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
20
Council charges
$2,743
Legal description
1753726, 5441986

How it went

  1. Application lodged
  2. Council asked for more information (s92)
  3. Applicant provided the information
  4. Granted

Properties

Not matched to a property.

Greater Wellington Regional's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/256839006
2023/2418825006
2022/238036206
2021/2235401—74
2020/21922619839