Granted

Water permit: To take groundwater (dewatering) during construction of building platform and retaining structures and…

To take groundwater (dewatering) during construction of building platform and retaining structures and take groundwater long-term WAT as per AEE - Michelle Creamer email dated 31.05.2022

Water permit · Auckland · lodged 16 Mar 2022

Council
Auckland
Consent number
WAT60403315
Kind
Water permit
Subtype
Divert - Groundwater
Application
New consent (s88)
Activity status
Restricted discretionary
Lodged
16 Mar 2022
Decided
10 Oct 2022
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
104
Legal description
Lot 9 DP 77398

How it went

  1. Application lodged
  2. Council asked for more information (s92)
  3. Applicant provided the information
  4. Granted

Properties

On 1 property, matched by the legal description the council gave.

Processed with

Auckland's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/255,2183,727—3427
2023/241,0062,94223942
2022/239392,72621222
2021/223,2112,43542117
2020/211,3263,9624832