Land use: To drill up to two bores including constructing one production bore. For the purpose of accessing groundwater
Land use · Otago Regional · lodged 24 Jul 2020
- Council
- Otago Regional
- Consent number
- RM20.241.01
- Kind
- Land use consent
- Subtype
- Bore Construction Consent
- Application
- New consent (s88)
- Activity status
- Controlled
- Lodged
- 24 Jul 2020
- Decided
- 19 Aug 2020
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 18
- Council charges
- $522
- Legal description
- LOT 1DP 5638
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Publicly notified
- Granted
Properties
On 2 properties, matched by the legal description the council gave.
Otago Regional's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 125 | 56 | 0 | 2 | 4 |
| 2023/24 | 98 | 45 | 1 | 3 | 3 |
| 2022/23 | 80 | 55 | 0 | 5 | 1 |
| 2021/22 | 114 | 45 | 1 | 7 | 4 |
| 2020/21 | 55 | 23 | — | — | 2 |