Resource: Condition 5 - Stormwater requires a detention tank to maintain peak discharge levels as the stormwater is…

Condition 5 - Stormwater requires a detention tank to maintain peak discharge levels as the stormwater is being discharged to the combined network. The requested change is to remove the requirement for detention.

Resource · Auckland · lodged 24 Aug 2020

Council
Auckland
Consent number
LUC60322229-A
Subtype
Dwelling(s)
Application
Change of conditions (s127)
Activity status
Discretionary
Lodged
24 Aug 2020
Decided
3 Sep 2020
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
8
Council charges
$1,278
Legal description
PT ALLOT 9 SEC 8 Suburbs AUCKLAND

How it went

  1. Application lodged — Change of conditions (s127)
  2. Granted — Change of conditions (s127)

Properties

On 37 properties, matched by the legal description the council gave.

Auckland's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/255,2183,727—3427
2023/241,0062,94223942
2022/239392,72621222
2021/223,2112,43542117
2020/211,3263,9624832