Granted

Land use: Construction Works Associated with Biomass Boiler Project

Land use · Timaru District · lodged 4 Oct 2024

Council
Timaru District
Consent number
102.2024.00000142.001
Kind
Land use consent
Subtype
Rural
Application
New consent (s88)
Activity status
Non-complying
Lodged
4 Oct 2024
Decided
13 Jan 2025
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
13
Council charges
$9,241
Legal description
LOT: 2 DP: 73281

How it went

  1. Application lodged
  2. Suspended until charges were paid
  3. Resumed after charges were paid
  4. Council commissioned an expert report (s92(2))
  5. Commissioned report received
  6. Granted

Properties

On 1 property, matched by the legal description the council gave.

Timaru District's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/25—————
2023/2432000
2022/2311000
2021/2200100
2020/2110100