Land use: The applicant is the new owner of the site which had been served an abatement notice. In order to resolve the…
The applicant is the new owner of the site which had been served an abatement notice. In order to resolve the unconsented earthworks undertaken by the previous owner, the applicant has engaged specialists to assess the unconsented works and provide a remediation p lan, as such consent is required because of the remedial works required to stabilise the site.
Land use · Auckland · lodged 16 Aug 2021
- Council
- Auckland
- Consent number
- LUC60384137
- Kind
- Land use consent
- Subtype
- Earthworks Residential
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 16 Aug 2021
- Decided
- 2 Mar 2022
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 124 (over the statutory limit)
- Council charges
- $2,876
- Legal description
- LOT 3 DP 196590
How it went
- Application lodged
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |