Land use: Earthworks for a building platform and access - proposed Lot 3 of stage 2 Bellbird Rise subdivision
Land use · Upper Hutt City · lodged 4 Oct 2024
- Council
- Upper Hutt City
- Consent number
- 2410104
- Kind
- Land use consent
- Subtype
- Earthworks
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 4 Oct 2024
- Decided
- 4 Dec 2024
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 20
- Council charges
- $1,240
- Legal description
- Lot 100 DP 568347
How it went
- Application lodged
- Suspended until charges were paid
- Resumed after charges were paid
- Council asked for more information (s92)
- Applicant provided the information
- Deferred until other consents are applied for (s91)
- Resumed after s91 deferral
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Upper Hutt City's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 9 | 4 | 0 | 0 | 0 |
| 2023/24 | 3 | 3 | — | — | — |
| 2022/23 | 6 | 9 | 0 | 0 | 0 |
| 2021/22 | 8 | 7 | 0 | 0 | 0 |
| 2020/21 | 11 | 9 | — | 0 | — |