Subdivision: To vary conditions on a subdivision consent that currently restrict earthworks and structures west of the…
To vary conditions on a subdivision consent that currently restrict earthworks and structures west of the 75.5m above mean sea level contour; and to provide for a retaining wall and earthworks on Mataura River Floodway.
Subdivision · Gore District · lodged 14 Mar 2019
- Council
- Gore District
- Consent number
- 013.2019.00000413.001
- Kind
- Subdivision consent
- Subtype
- Land Use - Earthworks
- Application
- Change of conditions (s127)
- Activity status
- Discretionary
- Lodged
- 14 Mar 2019
- Decided
- 22 Mar 2019
- Notification
- Not notified
- Hearing
- No
- Decided by
- Independent commissioner(s)
- Appealed to the Environment Court
- No
- Working days to decide
- 7
- Council charges
- $1,726
- Legal description
- Lot: 2 DP: 345589
How it went
- Deferred until other consents are applied for (s91) — Change of conditions (s127)
- Application lodged — Change of conditions (s127)
- Resumed after s91 deferral — Change of conditions (s127)
- Granted by independent commissioner(s) — Change of conditions (s127)
Properties
Not matched to a property.
Gore District's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | — | 0 | 0 | 0 | 0 |
| 2023/24 | 0 | 0 | 0 | 0 | 0 |
| 2022/23 | 0 | 0 | 0 | 0 | 0 |
| 2021/22 | 0 | 0 | 0 | 0 | 0 |
| 2020/21 | 0 | 0 | 0 | 0 | 0 |