Land use: Southern Renewals Project - Wastewater pipeline and pipe bridge replacements
Land use · Auckland · lodged 17 Nov 2016
- Council
- Auckland
- Consent number
- TRE60183942
- Kind
- Land use consent
- Application
- New consent (s88)
- Activity status
- Restricted discretionary
- Lodged
- 17 Nov 2016
- Decided
- 13 Jan 2017
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 25 (over the statutory limit)
- Legal description
- Lot 495 DP 41022
How it went
- Application lodged
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |