Land use: Undertake 4550 m³ of Land Disturbance, Recontouring, Cut, Fill and Compact 0.652 hectares of Land for…
Undertake 4550 m³ of Land Disturbance, Recontouring, Cut, Fill and Compact 0.652 hectares of Land for Whanganui Prison Raw Blackwater Pumpstation Building Platform and 9.5 Kilometer Pipeline Installation Development purposes at Pauri Domain Road, Kaitoke Road, State Highway 3, Wikitoria Road and Airport Road, Whanganui
Land use · Horizons Regional · lodged 28 Apr 2023
- Council
- Horizons Regional
- Consent number
- ATH-2023206008.00
- Kind
- Land use consent
- Subtype
- Land
- Application
- New consent (s88)
- Activity status
- Discretionary
- Lodged
- 28 Apr 2023
- Decided
- 28 Mar 2024
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 20
- Council charges
- $10,313
- Legal description
- SECS 2 3 SO 340748 SEC 1 SO 36413 LOT 2 DP 46128 SECS 478-480 PT SEC 475 LEFT BANK WANGANUI RIVER; SEC 1 SO 26708 SEC 1 SO 373103
How it went
- Suspended until charges were paid
- Application lodged
- Resumed after charges were paid
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Processed with
- ATH-2023206010.00 — Discharge permit, granted
- ATH-2023206009.00 — Water permit, granted
Horizons Regional's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 212 | 75 | 1 | 11 | 5 |
| 2023/24 | 238 | 60 | 1 | 10 | 7 |
| 2022/23 | 123 | 52 | 1 | 5 | 8 |
| 2021/22 | 15 | 43 | 0 | 28 | 0 |
| 2020/21 | 131 | 53 | 0 | 0 | 14 |