Granted

Land use: To install an underground cable in Root Protection Zone Resource consent is required under the Operative…

To install an underground cable in Root Protection Zone Resource consent is required under the Operative Hamilton City District Plan (ODP) to install a new electricity cable and associated ducting in the Transport Corridor Zone. Resource consent is specifically required due to the earthworks associated with the cable installation being within the vicinity of three Root Protection Zones of Notable Trees. The proposal complies with all other relevant standards of the ODP

Land use · Hamilton City · lodged 3 Apr 2025

Council
Hamilton City
Consent number
010.2025.00013333.001
Kind
Land use consent
Subtype
Network Utility
Application
New consent (s88)
Activity status
Restricted discretionary
Lodged
3 Apr 2025
Decided
13 May 2025
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
19
Council charges
$3,138
Legal description
Lot 29 DP 10808

How it went

  1. Application lodged
  2. Granted

Properties

Approximate: the land described has since been subdivided; placed among its plan's other lots

Hamilton City's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/25238000
2023/244612———
2022/23468000
2021/225716000
2020/21188000