Below: 10 commercial consents we hold in Torbay, searchable and on the map.

Consents we hold102 in the last 12 monthsSearch them ↓

Commercial consents on record in Torbay

Individual building consents we hold, each on its property: 10 from 1 Aug 2019 to 1 Nov 2025. Councils publish their records unevenly, so these are what we have, not every consent issued — for the full count, see the official figures above.

What the work is

Consents in the last five years by the kind of work their description names.

  1. Commercial alterations7

    2 in the last 12 months · typically $50k

Consents on record by month

The last three years. A recent dip is often records still to arrive.

01122202420252026November 2023: 0December 2023: 0January 2024: 0February 2024: 0March 2024: 0April 2024: 0May 2024: 0June 2024: 0July 2024: 0August 2024: 0September 2024: 0October 2024: 0November 2024: 0December 2024: 0January 2025: 0February 2025: 0March 2025: 0April 2025: 0May 2025: 0June 2025: 0July 2025: 0August 2025: 0September 2025: 1October 2025: 0November 2025: 2December 2025: 0January 2026: 0February 2026: 0March 2026: 0April 2026: 0May 2026: 0June 2026: 0July 2026: 0August 2026: 0September 2026: 0October 2026: 0

Largest in the last 12 months

  1. $600kRbw - renovation to an existing two storey, four bdrm, detached dwg. Alt to the media room, living, dining & kitchen, office, master bdrm, wc, ensuite & bathrm. Three new joine 7 Summit Drive
  2. $35kConstruction of workshop & stores 49 Waiau Street

10 consents

  1. Commercial alterations$35k

    Construction of workshop & stores

    49 Waiau Street · 1 Nov 2025 · BCN/2025/7274

  2. Commercial alterations$600k

    Rbw - renovation to an existing two storey, four bdrm, detached dwg. Alt to the media room, living, dining & kitchen, office, master bdrm, wc, ensuite & bathrm. Three new joine

    7 Summit Drive · 1 Nov 2025 · BCO10402386

  3. Commercial alterations$99k

    Rbw - no window or cladding changes. Internal alterations only. Gf: new bar, bathrm reconfiguration, minor wall changes. Ff: kitchen & hallway reconfigured, vanity added to wc, bathrm & mast

    25 Ian Sage Avenue · 1 Sep 2025 · BCO10400016

  4. Commercial alterations$50k

    Rbw - gge conversion to rumpus pool room. Recladding from vertical weatherboards to vertical aluminum paneling on cavity. Removal of existing joinery & new dbl glazed joinery installed. New plumbing fixtures toilet, shower, vanity, mini bar

    975 East Coast Road · 1 Sep 2022 · BCO10353736

  5. Commercial alterations$85k

    rbw - alt to ground level to convert gge into gym with new bathrm & entrance, move laundry to new kitchen & redo ensuite. Gge door closed off with new door & window. New spiral stairs to replace existing stairs. Redo upper-level

    286 Glenvar Road · 1 Jul 2022 · BCO10337611

  6. Commercial alterations$18k

    Rbw. Addtional bathrm to workshop & small area patch up of bevelback weatherboard.

    4 Foley Place · 1 Mar 2022 · BCO10345858

  7. Commercial alterations$10k

    Rbw - small extension to first floor, plus new hall & wardrobes

    17 Wairere Road · 1 Feb 2022 · BCO10338264

  8. New commercial buildings$1m

    rbw - demolish existing building completely. Proposed new two-storey dwg, including 5 bedrooms, kitchen, chinese kitchen, living, dining, laundry, office, toilet, gge

    11 Gilberd Place · 1 Apr 2020 · BCO10300432

  9. New commercial buildings$55k

    rbw - stockley site - two bdrm one bathrm factory built dwg to be moved to site where foundation, decks & connection to services will be carried out & is part of this consent. The factory built dwg will be issued with a ccc from f

    114 Deep Creek Road · 1 Nov 2019 · BCO10289113

  10. Commercial alterations$40k

    rbw - change existing gge to rumpus, add gym & bathrm.

    2/2 Danbury Drive · 1 Aug 2019 · BCO10289770

ResidentialCommercial The dots are this page of the list.

Near Torbay

Questions

What is a building consent?

Written approval from a council (a building consent authority) that planned building work complies with the Building Code. Most new buildings, additions, structural alterations, fires and plumbing and drainage work need one; some minor work is exempt under Schedule 1 of the Building Act 2004.

Where do these figures come from?

The official counts are Stats NZ’s monthly Building consents issued release (CC BY 4.0), covering every consent every council issues. The individual consents listed are ones we hold from councils’ records and other public sources; they are not a complete list for every council.

Official figures: Stats NZ, Building consents issued, licensed CC BY 4.0. Values are as declared on the consent, before GST, in the dollars of the day. Recent months are revised as late consents arrive. Council: Auckland Council.