Land use: Bulk earthworks and associated discharge of sediment laden water for retrospective works over 10,000m2 and…
Bulk earthworks and associated discharge of sediment laden water for retrospective works over 10,000m2 and the completion and stabilisation of this area.
Land use · Greater Wellington Regional · lodged 3 Dec 2024
- Council
- Greater Wellington Regional
- Consent number
- 40046*
- Kind
- Land use consent
- Subtype
- LUC - SOIL DISTURBANCE
- Application
- New consent (s88)
- Activity status
- Discretionary
- Lodged
- 3 Dec 2024
- Decided
- 9 May 2025
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 14
- Council charges
- $3,565
- Legal description
- Lot 3 DP 304134
How it went
- Application lodged
- Suspended until charges were paid
- Resumed after charges were paid
- Council told the applicant there are affected neighbours
- Applicant answered: neighbours’ approvals, or notify them
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
Not matched to a property.
Processed with
- 40047* — Discharge permit, granted
Greater Wellington Regional's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 68 | 39 | 0 | 0 | 6 |
| 2023/24 | 188 | 25 | 0 | 0 | 6 |
| 2022/23 | 80 | 36 | 2 | 0 | 6 |
| 2021/22 | 35 | 40 | 1 | — | 74 |
| 2020/21 | 92 | 26 | 1 | 98 | 39 |