Land use: Reclamation of the intermittent streams on site : Bundled consent for a staged combined integrated 60 lot…
Reclamation of the intermittent streams on site : Bundled consent for a staged combined integrated 60 lot residential subdivision, yard setback, height in relation to boundary infringments, on site parking infringements, shortfall of on-street parking, 2 JOAL serving a total of 15 lots - landscape strip and crossing infringement associated with JOAL, loss of two wetland areas comprising of a total of 1,067m², earthworks of approximatley 7,400 cut and 15,400 fill over an area of 2,2373 ha, earthworks within overland flow paths, earthworks involving reclamation of an existing permanent section of stream less than 3m in width, excavations infringing the 1:2 rule, removal of both native and exotic trees.
Land use · Auckland · lodged 29 Feb 2016
- Council
- Auckland
- Consent number
- REG-66889
- Kind
- Land use consent
- Application
- New consent (s88)
- Activity status
- Non-complying
- Lodged
- 29 Feb 2016
- Decided
- 16 Jun 2016
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 37
- Council charges
- $11,421
- Legal description
- Sec 2 SO 435211 (1.716HA)
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
On 1 property, matched by the legal description the council gave.
Auckland's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 5,218 | 3,727 | — | 34 | 27 |
| 2023/24 | 1,006 | 2,942 | 2 | 39 | 42 |
| 2022/23 | 939 | 2,726 | 2 | 12 | 22 |
| 2021/22 | 3,211 | 2,435 | 4 | 21 | 17 |
| 2020/21 | 1,326 | 3,962 | 4 | 8 | 32 |