Granted

Land use: To construct a bore for the purpose of accessing ground water

Land use · Otago Regional · lodged 13 Feb 2018

Council
Otago Regional
Consent number
RM18.050.01
Kind
Land use consent
Subtype
Bore
Application
New consent (s88)
Activity status
Controlled
Lodged
13 Feb 2018
Decided
22 Feb 2018
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
8
Council charges
$473
Legal description
Lot 2 DP 520080

How it went

  1. Application lodged
  2. Granted

Properties

Not matched to a property.

Otago Regional's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/2512556024
2023/249845133
2022/238055051
2021/2211445174
2020/215523——2