Granted

Discharge permit: for the temporary discharge of sediment contaminated stormwater to water and to land where it may…

for the temporary discharge of sediment contaminated stormwater to water and to land where it may enter water and within or within 100 metres from a natural wetland during earthworks to facilitate the development of a retirement village.

Discharge permit · Bay of Plenty Regional · lodged 2 Aug 2023

Council
Bay of Plenty Regional
Consent number
RM23-0349-DC.01
Kind
Discharge permit
Subtype
Discharge
Application
New consent (s88)
Activity status
Discretionary
Lodged
2 Aug 2023
Decided
30 May 2024
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
20
National environmental standard
NES Freshwater
Legal description
Lot 1 DP 555935 and Lot 2 DP 555935 (Tauranga City)

How it went

  1. Application lodged
  2. Council asked for more information (s92)
  3. Applicant provided the information
  4. Granted

Properties

Not matched to a property.

Processed with

Bay of Plenty Regional's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/2544183—27
2023/24811870718
2022/2368182067
2021/221125—2—
2020/21152125—2—