Discharge permit: set conditions for the temporary discharge of sediment contaminated stormwater to land where it may…
set conditions for the temporary discharge of sediment contaminated stormwater to land where it may enter water during earthworks at
Discharge permit · Bay of Plenty Regional · lodged 6 Dec 2022
- Council
- Bay of Plenty Regional
- Consent number
- RM22-0558-DC.02
- Kind
- Discharge permit
- Subtype
- Discharge
- Application
- New consent (s88)
- Activity status
- Discretionary
- Lodged
- 6 Dec 2022
- Decided
- 2 Jul 2024
- Notification
- Not notified
- Hearing
- No
- Decided by
- Local authority officer
- Appealed to the Environment Court
- No
- Working days to decide
- 17
- Legal description
- Lot 2 DP 560362 8233823 - Section 1 SO 567445
How it went
- Application lodged
- Council asked for more information (s92)
- Applicant provided the information
- Granted
Properties
Not matched to a property.
Processed with
- RM22-0558-LC.01 — Land use, granted
- RM22-0558-DC.01 — Discharge permit, granted
Bay of Plenty Regional's RMA enforcement
The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.
| Year | Actions | Abatement notices | Enforcement orders | Prosecutions | Convictions |
|---|---|---|---|---|---|
| 2024/25 | 44 | 183 | — | 2 | 7 |
| 2023/24 | 81 | 187 | 0 | 7 | 18 |
| 2022/23 | 68 | 182 | 0 | 6 | 7 |
| 2021/22 | 1 | 125 | — | 2 | — |
| 2020/21 | 152 | 125 | — | 2 | — |