Granted

Land use: Operative District Plan: To construct a second dwelling which is unable to comply with building coverage,…

Operative District Plan: To construct a second dwelling which is unable to comply with building coverage, impervious surfaces, traffic movement and earthwork requirements. Retrospective consent is also required for existing non-habitable buildings within the permitted boundary setbacks. Waikato District Plan - Operative in Part: To construct a non-compliant minor residential unit which is also unable to comply with building coverage, and earthwork requirements. Retrospective consent is required for existing non-habitable buildings within the permitted boundary setbacks.

Land use · Waikato District · lodged 27 Nov 2024

Council
Waikato District
Consent number
LUC0194/25
Kind
Land use consent
Subtype
Rural-Residential Second/DPD/Subsidiary Dwelling/Minor Resident Unit Building Coverage/GFA Impervious Surfaces earthworks, traffic movement
Application
New consent (s88)
Activity status
Discretionary
Lodged
27 Nov 2024
Decided
21 Mar 2025
Notification
Not notified
Hearing
No
Decided by
Local authority officer
Appealed to the Environment Court
No
Working days to decide
26 (over the statutory limit)
Council charges
$5,582
Legal description
Lot 1 DPS 53463

How it went

  1. Application lodged
  2. Council asked for more information (s92)
  3. Applicant provided the information
  4. Granted

Properties

Not matched to a property.

Waikato District's RMA enforcement

The council's totals across its whole area, as it reported them to MfE. Not about this consent or this site: no record of individual breaches is published.

YearActionsAbatement noticesEnforcement ordersProsecutionsConvictions
2024/25545000
2022/2394001
2021/22265010
2020/21598021
2019/2093010