Building consents

Building consents in Macandrew Bay

Below: 136 consents we hold in Macandrew Bay, searchable and on the map.

Consents we hold13612 in the last 12 monthsSearch them ↓

Consents on record in Macandrew Bay

Individual building consents we hold, each on its property: 136 from 1 Sep 2019 to 1 Aug 2026. Councils publish their records unevenly, so these are what we have, not every consent issued — for the full count, see the official figures above.

What the work is

Consents in the last five years by the kind of work their description names.

  1. Fires and heating25

    3 in the last 12 months · typically $6,000

  2. Alterations and additions23

    1 in the last 12 months · typically $25k

  3. New homes7

    1 in the last 12 months · typically $600k

  4. Plumbing, drainage and wastewater6

    2 in the last 12 months · typically $13k

  5. Decks, pergolas and verandahs6

    2 in the last 12 months · typically $20k

  6. Retaining walls4

    1 in the last 12 months · typically $8,500

  7. Demolition3

    typically $80k

  8. Insulation2

    1 in the last 12 months · typically $3,500

  9. Minor dwellings and sleepouts1

    1 in the last 12 months · typically $1

  10. Garages, sheds and carports1

    typically $3,000

Consents on record by month

The last three years. A recent dip is often records still to arrive.

01234202420252026November 2023: 2December 2023: 1January 2024: 1February 2024: 1March 2024: 1April 2024: 2May 2024: 1June 2024: 1July 2024: 1August 2024: 1September 2024: 1October 2024: 2November 2024: 1December 2024: 0January 2025: 1February 2025: 0March 2025: 2April 2025: 0May 2025: 3June 2025: 1July 2025: 0August 2025: 0September 2025: 2October 2025: 4November 2025: 1December 2025: 2January 2026: 3February 2026: 0March 2026: 0April 2026: 0May 2026: 1June 2026: 1July 2026: 2August 2026: 2September 2026: 0October 2026: 0

Largest in the last 12 months

  1. $700kAlt & extend internal layout of dwg with deck, construct retaining wall 1 Barling Street
  2. $650kNew dwg with attached gge, install escea tfs650 heater & construct retaining walls (proposed lot 2) create future drain in common 21 Porterfield Street
  3. $250kExtend dwg to form bedrooms, relocate bathrm, form ensuite, install solid fuel burner, construct deck 65 Marion Street
  4. $35kAdd deck to dwg 17 McLelland Street
  5. $18kForm toilet in basement, add concrete slab to sub-floor of dwg 9 St Ronans Road

136 consents

  1. Minor dwellings and sleepouts$1

    Amendment to aba-2024-1882 - delete sleepout, install handrails

    35 Bayne Terrace · 1 Aug 2026 · 487/26

  2. Insulation$2,000

    Install insulation to external walls of dwg

    65 Greenacres Street · 1 Aug 2026 · 842/26

  3. Decks, pergolas and verandahs$35k

    Add deck to dwg

    17 McLelland Street · 1 Jul 2026 · 676/26

  4. Plumbing, drainage and wastewater$18k

    Form toilet in basement, add concrete slab to sub-floor of dwg

    9 St Ronans Road · 1 Jul 2026 · 736/26

  5. Alterations and additions$250k

    Extend dwg to form bedrooms, relocate bathrm, form ensuite, install solid fuel burner, construct deck

    65 Marion Street · 1 Jun 2026 · 346/26

  6. Decks, pergolas and verandahs$700k

    Alt & extend internal layout of dwg with deck, construct retaining wall

    1 Barling Street · 1 May 2026 · 1766/25

  7. Fires and heating$7,000

    Install maxen Henley 250-l heater in dwg

    22 Wharfdale Street · 1 Jan 2026 · 1896/26

  8. Plumbing, drainage and wastewater$4,000

    Install toilet in bathrm in dwg

    50 Greenacres Street · 1 Jan 2026 · 3/26

  9. Fires and heating$7,000

    Install metro wee rad leg heater in dwg

    14 Hellyer Street · 1 Jan 2026 · 33/26

  10. Retaining walls$8,000

    Construct permacrib retaining wall

    417 Portobello Road · 1 Dec 2025 · 1526/25

  11. Fires and heating$5,000

    Install maxen Saint Clair 350 heater in dwg

    26 Jane Street · 1 Dec 2025 · 1813/25

  12. New homes$650k

    New dwg with attached gge, install escea tfs650 heater & construct retaining walls (proposed lot 2) create future drain in common

    21 Porterfield Street · 1 Nov 2025 · 1384/25

  13. Plumbing, drainage and wastewater$5,000

    Construct foul & stormwater drainage

    415 Portobello Road · 1 Oct 2025 · 1395/25

  14. Plumbing, drainage and wastewater$47k

    Construct foul & stormwater drainage

    416 Portobello Road · 1 Oct 2025 · 1397/25

  15. Fires and heating$7,000

    Install metro tiny rad leg heater in dwg

    64 Marion Street · 1 Oct 2025 · 1606/25

  16. Alterations and additions$1.2m

    Rbw - alt to an existing house with an extension consisting of plater system on cavity with a warm membrane roof. A new outdoor spa within an existing pool area & renovation to interiors incl

    15 Marine Parade · 1 Oct 2025 · BCO10398129

  17. Alterations and additions$50k

    Alt layout of bathrooms (wet-area showers) & install hot water system

    21 Greenacres Street · 1 Sep 2025 · 1194/25

  18. Fires and heating$6,000

    Install maxen kinmont 350-p heater in dwg

    11 Wharfdale Street · 1 Sep 2025 · 1420/25

  19. Fires and heating$2,000

    Install yunca monte base heater with wet-back in dwg

    15 McLelland Street · 1 Jun 2025 · 360/25

  20. Decks, pergolas and verandahs$5,000

    Amendment to aba-2022-398 - enlarge deck & revise structure & retaining wall

    11 Kellas Street · 1 May 2025 · 465/25

  21. Fires and heating$5,000

    Install yunca monte base heater with wetback in dwg

    17 Jane Street · 1 May 2025 · 517/25

  22. Fires and heating$6,000

    Install woodsman flare heater in dwg

    21 Greenacres Street · 1 May 2025 · 753/25

  23. Alterations and additions$5,000

    Amendment to aba-2024-1400 - alt exterior wall framing & roof

    26 Greenacres Street · 1 Mar 2025 · 124/25

  24. Fires and heating$8,000

    Install champion tria heater in dwg

    15 Greenacres Street · 1 Mar 2025 · 273/25

  25. Alterations and additions$15k

    Alt dwg - remove walls & install beams to create open-plan kitchen, living & dining, enlarge bedrooms

    14 Featherston Street · 1 Jan 2025 · 2142/24

ResidentialCommercial The dots are this page of the list.

Near Macandrew Bay

Questions

What is a building consent?

Written approval from a council (a building consent authority) that planned building work complies with the Building Code. Most new buildings, additions, structural alterations, fires and plumbing and drainage work need one; some minor work is exempt under Schedule 1 of the Building Act 2004.

Where do these figures come from?

The official counts are Stats NZ’s monthly Building consents issued release (CC BY 4.0), covering every consent every council issues. The individual consents listed are ones we hold from councils’ records and other public sources; they are not a complete list for every council.

Official figures: Stats NZ, Building consents issued, licensed CC BY 4.0. Values are as declared on the consent, before GST, in the dollars of the day. Recent months are revised as late consents arrive. Council: Dunedin City Council.